About photovoltaic parks
A photovoltaic park brings together hundreds or thousands of panels that convert light into electricity. Real efficiency comes from proper design, suitable location, and well-thought-out grid connection. That's where we come in.
Design and Development of a Park
We identify the location, conduct a pre-feasibility/feasibility study, prepare the documentation for urban planning and authorization, define the technical connection solution and the technical design. The end result: a bankable project with no surprises along the way.
Construction and commissioning (EPC)
We take over the project and put it into production: civil/mechanical/electrical works, structure and panel installation, SCADA and protection settings, testing, acceptance, and connection certificate. We deliver as-built documentation, warranties, and training.
Photovoltaic Park Design Services

From the sun, straight into production
We develop projects that produce
Photovoltaic parks developed by EMAS Energy
| Project | PV (MWp) | BESS (MWh) |
|---|---|---|
| Gogosari, GR Sold | 30.6 | 120 |
| Corbu, OT | 42.9 | 172 |
| Corbu 1, OT Sold | 45.5 | 182 |
| Corbu 2, OT Sold | 22.9 | 88 |
| Laza, VS | 31.5 | 120 |
| Maureni 1, CS | 43.5 | 175 |
| Maureni 2, CS Sold | 24.15 | 96 |
| Scortaru Nou, BR Sold | 26.7 | 100 |
| Scortaru Nou 2, BR Sold | 45 | 180 |
| Saligny, CT | 46.3 | 184 |
| Hida, SJ | 93.6 | |
| Hida 2, SJ | 50 | |
| Avram Iancu, BH Sold | 41.40 | |
| Cojani 1, GJ Sold | 45.2 | |
| Cojani 2, GJ Sold | 46.5 | |
| Cojani 3, GJ Sold | 43.8 | |
| Cuza Voda 1, CT Sold | 28 | |
| Cuza Voda 2, CT Sold | 34.49 | |
| TOTAL | 742.04 | 1417 |
What we deliver
Construction of photovoltaic parks
We take over the project from ATR and PT/DDE until commissioning and connection certificate. You receive an asset ready to produce energy.
Partner for serious projects